10 men or 16 women can complete a work in 40 days. In how many days 40 women and 15 men together can complete the same work?
10 men or 16 women can complete a work in 40 days. In how many days 40 women and 15 men together can complete the same work?
Work done by 10 men = work done by 16 women
Work done by 15 men = work done by (16*3/2) women
=24 women
So, 40 women and 15 men = 40 women and 24 women
= 64 women
Therefore we can say
16 women will take 40 days
Hence, 64 women will take 40/4 =10 days
Similar Questions for you
It's difficult but in some colleges you may can get
is collinear with
⇒ = …(1)
is collinear with
⇒ …(2)
From (1) and (2)
->
and
, put sin3x + cos3x = t(3 sin2x×cosx – 3cos2xsinx) dx = dt
->
Taking an Exam? Selecting a College?
Get authentic answers from experts, students and alumni that you won't find anywhere else.
On Shiksha, get access to
Learn more about...

Quantitative Aptitude Prep Tips for MBA 2025
View Exam DetailsMost viewed information
SummaryDidn't find the answer you were looking for?
Search from Shiksha's 1 lakh+ Topics
Ask Current Students, Alumni & our Experts
Have a question related to your career & education?
See what others like you are asking & answering