12 boys do 4/7 of a work in 20 days. How many extra boys must be employed to finish the remaining work in 6 days?
12 boys do 4/7 of a work in 20 days. How many extra boys must be employed to finish the remaining work in 6 days?
Option 1 -
15 boys
Option 2 -
12 boys
Option 3 -
16 boys
Option 4 -
18 boys
-
1 Answer
-
Correct Option - 4
Detailed Solution:The work done by 12 boys in 20 days =
So, remaining work need to be done in 6 days =
We get, M2 = 30. Hence, 18 extra boys are required.