Mahesh and Anand together can polish the floors of a building in 60 days. Mahesh alone can complete (1\4) part of the total work in 45 days. In how many days Anand alone can polish the floor of the same building?
Mahesh and Anand together can polish the floors of a building in 60 days. Mahesh alone can complete (1\4) part of the total work in 45 days. In how many days Anand alone can polish the floor of the same building?
Total days taken by Mahesh alone = 45*4 = 180 days
Let the total work = 180 units (LCM of 180 and 60)
Mahesh per day work = 1 units
Mahesh and Anand per day work = 180/60 = 3 units
Anand per day work = 3 – 1 = 2
Time taken = 180/2 = 90 days
Similar Questions for you
It's difficult but in some colleges you may can get
is collinear with
⇒ = …(1)
is collinear with
⇒ …(2)
From (1) and (2)
->
and
, put sin3x + cos3x = t(3 sin2x×cosx – 3cos2xsinx) dx = dt
->
Taking an Exam? Selecting a College?
Get authentic answers from experts, students and alumni that you won't find anywhere else.
On Shiksha, get access to
Learn more about...

Quantitative Aptitude Prep Tips for MBA 2026
View Exam DetailsMost viewed information
SummaryDidn't find the answer you were looking for?
Search from Shiksha's 1 lakh+ Topics
Ask Current Students, Alumni & our Experts
Have a question related to your career & education?
See what others like you are asking & answering