Mahesh and Anand together can polish the floors of a building in 60 days. Mahesh alone can complete (1\4) part of the total work in 45 days. In how many days Anand alone can polish the floor of the same building?

Option 1 -

90 days 

Option 2 -

120 days

Option 3 -

75 days

Option 4 -

72 days

0 1 View | Posted a month ago
Asked by Shiksha User

  • 1 Answer

  • P

    Answered by

    Payal Gupta | Contributor-Level 10

    a month ago
    Correct Option - 1


    Detailed Solution:

    Total days taken by Mahesh alone = 45*4 = 180 days

    Let the total work = 180 units (LCM of 180 and 60)

    Mahesh per day work = 1 units

    Mahesh and Anand per day work = 180/60 = 3 units

    Anand per day work = 3 – 1 = 2

    Time taken = 180/2 = 90 days

Get authentic answers from experts, students and alumni that you won't find anywhere else

Sign Up on Shiksha

On Shiksha, get access to

  • 65k Colleges
  • 1.2k Exams
  • 688k Reviews
  • 1800k Answers

Learn more about...

Share Your College Life Experience

Didn't find the answer you were looking for?

Search from Shiksha's 1 lakh+ Topics

or

Ask Current Students, Alumni & our Experts

×
×

This website uses Cookies and related technologies for the site to function correctly and securely, improve & personalise your browsing experience, analyse traffic, and support our marketing efforts and serve the Core Purpose. By continuing to browse the site, you agree to Privacy Policy and Cookie Policy.

Need guidance on career and education? Ask our experts

Characters 0/140

The Answer must contain atleast 20 characters.

Add more details

Characters 0/300

The Answer must contain atleast 20 characters.

Keep it short & simple. Type complete word. Avoid abusive language. Next

Your Question

Edit

Add relevant tags to get quick responses. Cancel Post